Manomay Tex India (MANOMAY) to Build a ₹49 Crore Solar Plant

Reviewed by Vinayak Gandhi, CFA

Manomay Tex India is making a strategic move to lock in its energy costs. The denim maker will invest ₹48.6 crore to build a captive solar power plant in Rajasthan, aiming to shield its operations from volatile electricity prices.

The new 8.8 MW AC system, detailed in the NSE filing, will supply power to its denim and spinning units in Chittorgarh. The project is a significant scale-up of its renewable energy base, according to Tijori Alerts, and targets completion within the 2026-27 financial year. This comes as the company grapples with margin pressure, where a 55% surge in material costs recently outpaced its 41% revenue growth.

Key Points

  • The company will install an 8.8 MW AC solar plant in Chohtan, Barmer, at an estimated cost of ₹48.6 crore, excluding GST.
  • The generated power will be used for its Gangrar denim and Undawa spinning units in Chittorgarh, Rajasthan.
  • The project aims to enhance renewable power supply and ensure long-term cost efficiency for manufacturing.
  • Completion is scheduled for the 2026-27 financial year, adding to a recent slate of capital expenditures.

Hexa Perspective

This investment is a direct response to the cost pressures highlighted in the company's latest results. For a business where profit margins are thin and sensitive to input costs, securing a stable, lower-cost power source is a logical defensive move.

The project's success hinges on two factors: timely execution without straining the company's already leveraged balance sheet, and the realization of projected savings. A general industry guide from Solabrix suggests captive solar for textile mills can have payback periods around 2.3 years, but Manomay's specific returns are unstated. If the plant delivers as planned, it could provide a durable boost to operating efficiency, making the recent capacity expansion more sustainable.

Trending news


Want this applied to your portfolio?

Talk to a HexaWealth advisor, or sync your mutual fund data for insights tailored to your holdings.

Share or follow HexaWealth

Manomay Tex India (MANOMAY) to Build a ₹49 Crore Solar Plant

Frequently asked questions

What is Manomay Tex India's solar power project?
Manomay Tex India is installing an 8.80 MW AC solar power generating system in Chohtan, Barmer, Rajasthan. The project, costing approximately ₹48.6 crore, will supply power to the company's denim and spinning units in Chittorgarh and is targeted for completion in the 2026-27 financial year.
How much is Manomay Tex investing in the solar plant?
According to the company's NSE filing, Manomay Tex India's estimated investment for the solar power project is ₹48.60 crore, excluding applicable GST. This capital expenditure aims to enhance renewable energy supply for its manufacturing operations.
Where will Manomay Tex's solar power plant be located?
The solar power plant will be located in Chohtan, Barmer district, Rajasthan. The power generated will be supplied to the company's manufacturing units situated in the Chittorgarh district, as reported by ScanX.
When will Manomay Tex's solar project be completed?
Manomay Tex India has scheduled the completion of its 8.8 MW solar power project for the 2026-27 financial year. The company aims to have the plant operational within this timeframe to start supplying power to its Chittorgarh units.
Why is Manomay Tex building a solar power plant?
Manomay Tex India is building the solar plant to enhance its renewable power supply and ensure long-term cost efficiency for its textile manufacturing. This move comes as the company faces margin pressure from rising input costs, aiming to stabilize a key operational expense.
What units will the Manomay Tex solar plant power?
The solar power generated will supply Manomay Tex India's Denim Unit and its Spinning Unit, both located in Chittorgarh, Rajasthan. The project is designed to provide renewable energy directly to these primary manufacturing sites.