Oval Projects (OVAL) Q2 FY27 Profit Stalls as Costs Outpace 20% Revenue Growth

The infrastructure EPC firm posted a 20% rise in Q2 FY27 revenue, but profit was flat as expenses surged and working capital bled cash.

Reviewed by Anant Kacholia, HexaWealth Research · Created 6 November 2026

Oval Projects Engineering's Q2 FY27 results show a clear squeeze. Revenue grew 20% year-on-year, but profit was flat as material and employee costs soared. Management cites a lumpy revenue cycle and a ₹500 crore bid pipeline for future growth.

For Oval Projects Engineering, the September quarter was a story of growth that never reached the bottom line. The infrastructure EPC player saw healthy top-line expansion, but the cost of securing that work ate directly into profitability, raising questions about its ability to scale profitably.

The numbers tell a clear tale of pressure. Revenue for Q2 FY27 stood at ₹71 crore, a 20% increase from the same quarter last year. Yet, profit remained flat at ₹6 crore. This pushed the net profit margin down 170 basis points to 8.5%.

Revenue & profit

Revenue (₹ Cr)

Profit (₹ Cr)

Revenue & profitQ2 FY26 59.0, Q4 FY26 91.0, Q2 FY27 71.0. Q2 FY26 6.0, Q4 FY26 8.0, Q2 FY27 6.0050100150200Q2 FY26Q4 FY26Q2 FY27
  • Revenue (₹ Cr), Q2 FY26: 59.0
  • Revenue (₹ Cr), Q4 FY26: 91.0
  • Revenue (₹ Cr), Q2 FY27: 71.0
  • Profit (₹ Cr), Q2 FY26: 6.0
  • Profit (₹ Cr), Q4 FY26: 8.0
  • Profit (₹ Cr), Q2 FY27: 6.0

Revenue (₹ Cr)

Revenue (₹ Cr)Q2 FY26 59.0, Q4 FY26 91.0, Q2 FY27 71.0050100150200Q2 FY26Q4 FY26Q2 FY27
  • Revenue (₹ Cr), Q2 FY26: 59.0
  • Revenue (₹ Cr), Q4 FY26: 91.0
  • Revenue (₹ Cr), Q2 FY27: 71.0

Profit (₹ Cr)

Profit (₹ Cr)Q2 FY26 6.0, Q4 FY26 8.0, Q2 FY27 6.005101520Q2 FY26Q4 FY26Q2 FY27
  • Profit (₹ Cr), Q2 FY26: 6.0
  • Profit (₹ Cr), Q4 FY26: 8.0
  • Profit (₹ Cr), Q2 FY27: 6.0

Net Profit Margin

Net Profit MarginQ2 FY26 10.2%, Q4 FY26 8.8%, Q2 FY27 8.5%0%5%10%15%20%Q2 '26Q4 '26Q2 '27
  • Net Profit Margin, Q2 FY26: 10.2%
  • Net Profit Margin, Q4 FY26: 8.8%
  • Net Profit Margin, Q2 FY27: 8.5%
MetricCurrentQ2 FY27Same quarter LYQ2 FY26
Revenue (₹ Cr)
71.0YoY +20%
59.0
Profit (₹ Cr)
6.0YoY 0%
6.0
Net Profit Margin
8.5%YoY -17%
10.2%

The Cost of Winning Work

The margin compression was driven by expenses that grew faster than sales. According to a MarketPing report, total costs rose 23.4%, led by a 40.5% jump in material costs and an 89% surge in employee expenses. Management, on the earnings call, attributed part of the EBITDA margin drop to work-in-progress accounting and higher upfront mobilization finance costs.

This cost surge is not a one-off but a structural feature of its growth model. The company's CFO acknowledged on the call that working capital will remain a drag, with operating cash flow negative at ₹5.69 crore for the first half. He estimated it could take one to two years for cash flow to turn positive.

A Strong Pipeline Meets Execution Friction

The counterbalance is a robust order book that provides visibility. Oval Projects reported a total order book of ₹806.8 crore as of November, with ₹473.86 crore yet to be executed. Management is targeting ₹200 crore in new order additions this fiscal year, split between December and March.

Live Chart

· OVAL

(BSE)

ISIN: INE0RTI01017

Analysts note the tension between this strong pipeline and the current execution challenges. A Stockwatch.live analysis pointed out that the 47% drawdown in the stock price from its high reflects real concerns over profit decline despite growth and persistent negative cash flow. The firm trades at a PE of 7.2, a significant discount to the industry average of 23.5.

Key Points

  • Revenue grew 20% year-on-year, but profit was completely flat, highlighting severe margin pressure from rising input and employee costs.
  • Operating cash flow remained deeply negative at -₹5.69 crore for H1 FY27, a structural headwind the CFO says may take 1–2 years to resolve.
  • A strong order book of ₹807 crore and a ₹500 crore tender pipeline underpin growth targets, but profitability on new orders is now the critical watchpoint.

Hexa Perspective

The quarter reveals Oval Projects as a company caught between a promising opportunity and a costly reality. The unexecuted order book offers multi-year revenue visibility, and management's guidance for ₹200 crore in new orders this year seems achievable.

Yet, the path to a re-rating is blocked by the margin and cash flow story. Investors are effectively paying for growth today while waiting for proof that this growth can be converted into sustainable profit and cash. The stock's deep discount to the sector reflects this execution skepticism, which will only lift with consistent quarterly evidence of margin recovery and cash generation.

Share or follow HexaWealth

Also read

Want this applied to your portfolio?

Talk to a HexaWealth advisor, or sync your mutual fund data for insights tailored to your holdings.

Oval Projects Engineering (OVAL) Q2 FY27 results, revenue and profits.

Frequently asked questions

What were Oval Projects Engineering's Q2 FY27 results?
For Q2 FY27 (quarter ended September 2026), Oval Projects Engineering reported revenue of ₹71 crore, a 20.3% increase year-on-year. Profit was flat at ₹6 crore. The net profit margin contracted to 8.5% from 10.2% in Q2 FY26 due to a faster rise in expenses.
Why did Oval Projects Engineering's profit not grow despite higher revenue in Q2 FY27?
Oval Projects' profit stalled because total expenses grew 25.5% year-on-year, outpacing the 20.3% revenue growth. A MarketPing report noted material costs jumped 40.5% and employee costs rose 89%. Higher finance costs and work-in-progress timing also pressured profitability, as per management commentary.
What is Oval Projects Engineering's current order book?
As of November 2026, Oval Projects Engineering's total order book stands at ₹806.8 crore. Of this, ₹473.86 crore is unexecuted, providing visibility for future revenue. Management is targeting ₹200 crore in new order additions during the remainder of FY27.
Why did Oval Projects Engineering's net profit margin contract in Q2 FY27?
The net profit margin contracted 170 basis points to 8.5% because costs rose faster than revenue. Management, cited by Sovrenn.com, attributed the EBITDA margin drop to WIP being accounted for at cost, higher upfront mobilization finance costs, and normal decreases from net work-in-progress.
What guidance did Oval Projects management provide for FY27?
Management guided for ₹200 crore in new order additions for FY27, expecting ₹100 crore by December 2026 and another ₹100 crore by March 2027. The long-term ambition is to reach ₹900–1,000 crore in revenue by FY30, subject to project awards.
What are analysts' main concerns about Oval Projects Engineering's margins?
Analysts are concerned that margin compression is structural, not temporary. A Stockwatch.live analysis highlighted a 103-basis-point drop in the EBITDA margin, which management understated. The negative operating cash flow and rising finance costs as the order book scales are seen as persistent headwinds to profitability.
Did Oval Projects Engineering's Q2 FY27 results beat analyst estimates?
There is no record of published analyst estimates being missed or beaten, as this was the company's first earnings call. The results themselves presented a mixed picture: revenue growth met expectations of solid expansion, but the flat profit and margin decline raised execution concerns among analysts reviewing the call.
What is the update on Oval Projects Engineering's working capital situation?
Working capital remains a significant drag. For H1 FY27, operating cash flow was negative ₹5.69 crore. The CFO attributed this to inventory builds and advances to vendors, noting it's a structural feature of their EPC cycle and may take 1–2 years to turn positive.
What are Oval Projects Engineering's major new project bids?
Management's pipeline includes bids for ONGC projects, a ₹150 crore water supply project in Agartala, and the second phase of an IGDL pipeline. They are also in advanced discussions with private sector players like GFL for lithium-ion battery plants and Chatterjee International for oil & gas work.
Oval Projects Engineering Q2 FY27 results net profit
Oval Projects Engineering's net profit for Q2 FY27 (September 2026 quarter) was ₹6 crore. This was flat compared to the ₹6 crore profit in Q2 FY26, despite a 20.3% increase in revenue during the period.
Oval Projects Engineering Q2 FY27 results order book
In its Q2 FY27 results announcement, Oval Projects Engineering reported a total order book of ₹806.8 crore as of November 2026. The unexecuted portion of this order book is ₹473.86 crore, spread across more than 41 active projects.